Solar Panel Installation @ Harry West Gym and LRC

Harry West Gym Alerts
Project Name / Area Approximate: Harry West Gym
Start Dates: 10/25/2010 to 12/31/2010
Emergency Contact: Ryan Murphy- 858-682-6968 Thomas J. Fine 619-994-4262, Guy Meades 619-994-5154, Rachel Fornaca - 619-994-8443, Paul Wraa- 858-922-5169
Construction Alert Description: CONSTRUCTION COMPLETED
Comments: Please notify City College Business Services for other alerts as observed.
Solar Panel Installation @ Harry West Gym and LRC/R Bldg Status
Project: Solar Panel Installation @ Harry West Gym and LRC/R Bldg
Description: Installation of Solar Panels on the roof of HWG and LRC Bldgs.
Location: Harry West Gym on Park Blvd and LRC Bldg on Park Blvd between B and C Streets
Start Date: 10/27/2010
Finish Date: 12/31/2010
Phase: Construction
Funding:
Comments: As of 02/2011- Contractor completed the installation of solar panels on roof of LRC Bldg and Harry West Gym in late 01/2011.  The District Construction Manager and Campus PM's office is now working with the contractor to complete the commissioning of the system.